The designed retaining system is composed of a slurry wall braced at its top. The bracing leans on a 130 m diameter circular reinforced concrete beam supported by piles that are linked with a buried circular internal slurry wall located at the excavation’s bottom.
Aim of monitoring:
The aims of the monitoring were to monitor the load on the circular internal slurry wall; sensors were placed tangentially on the rebar cage before the concrete pouring. Mat foundation was also monitored to control the thrusts of the external slurry wall.
INSTALLATION PERIOD | TYPE OF SENSORS | NUMBER OF SENSORS |
2001 | SOFO | 50 |